Fabritec Docs
English
  • English
  • Arabic
Learning Center
Support CenterChangelog
Learning Center
Support CenterChangelog
English
  • English
  • Arabic
English
  • English
  • Arabic
  1. Projects
  • Introductions
  • Installing Fabritec as a Desktop or Mobile App
  • Notification Settings and Push Notifications
  • Connecting Fabritec with AI Assistants: Claude AI and ChatGPT
  • Fabritec Production Setup & User Management
    • Production Setup
      • Production Stages
      • WorkStations
      • Categories
      • Routes
      • Labour Titles
      • Shifts
      • Labours
      • Labour Group
    • User Management
      • Roles
      • Departments
      • Users
      • Logs
    • Settings
      • Company Profile
      • Preferences
      • License Info
      • Settings
  • General
    • Home
    • Customers
    • Dashboards
    • Reports
    • User Profile & Change Language
    • Projects
      • Create New Project
      • Overview
      • Details
      • Buildings
      • Documents
      • Messages
      • Phases
      • Phases Explorer
      • Revisions: Bulk Paint Update & Selective Item Deletion
      • Phases Explorer: Manual Item Entry, Drawing Validation, and Smart Allocation
      • Routing Setup
      • Tracking
      • Quality Control
      • Shipping Status
      • Shipping
      • Erection
  • Menu
    • Folder Structure
    • Task Manager
    • Task Templates & Schedule View
    • Production Page
    • Revert & Refabricate Items in Production
    • Quality Control
    • Shipping Yard
    • Shipping Calendar
  • Fabritec Workflow
    • Fabritec Project Lifecycle workflow
    • Fabritec Dashboards and Reports workflow
    • Production Setup & User Management Workflow
  1. Projects

Shipping Status

The Shipping Status page allows you to monitor and manage all activities related to items entering the shipping yard and items ready for shipment.
This page connects production, QC, and logistics to ensure every item is properly tracked until it leaves the factory.
Shipping Status is divided into two main sections:
** Shipping Status** — View and manage all completed items, their weights, quantities, and shipment readiness.
** Entry to Shipping Yard** — Approve items entering the yard after QC.

b610b1fb-423e-490d-b85c-d7e1d9822cd5.png#

Before Shipping: Release the Phase for Shipping#

Before the shipping team starts dispatch planning or shipment execution for a phase, the phase should be officially released for shipping.
image.png
This release is controlled from the Phases page, not directly from the Shipping Status page.
Releasing a phase for shipping confirms that the phase is ready to move into the shipping workflow and that the shipping team can start preparing dispatches based on approved phase readiness.
This helps ensure that:
The phase has been released for production
Production and QC progress have been reviewed
Yard readiness has been confirmed
The shipping team is allowed to proceed
Dispatch planning is based on an approved phase status
When a phase is not released for shipping, the Shipping status remains false in the Phases table.

How to Release a Phase for Shipping#

To release a phase for shipping:
1.
Go to Projects → Select Project → Phases
2.
Find the required phase in the table
3.
Open the ⋮ actions menu
4.
Click Release for Shipping
5.
The Shipping status changes to true
Once the phase is released for shipping, the team can continue managing shipping readiness, preparing dispatches, and planning shipment execution.

Unrelease for Shipping#

Fabritec also allows authorized users to reverse the shipping release if the phase needs to be reviewed again before shipping continues.
image.png
After a phase is released for shipping, the action menu changes from Release for Shipping to Unrelease for Shipping.
Use Unrelease for Shipping when the phase was released too early, released by mistake, or needs another readiness review before dispatch planning continues.
This is useful when:
The phase was released for shipping before confirming readiness
The shipping team needs to recheck the phase status
There are pending production, QC, or yard readiness concerns
Dispatch planning should be paused temporarily
The team needs to prevent shipping actions until the phase is reviewed again

How to Unrelease a Phase from Shipping#

To unrelease a phase from shipping:
1.
Go to Projects → Select Project → Phases
2.
Find the required phase in the table
3.
Open the ⋮ actions menu
4.
Click Unrelease for Shipping
5.
The Shipping status changes back to false
After using Unrelease for Shipping, the phase is no longer treated as released for shipping.
The team can review the phase status and release it for shipping again when readiness is confirmed.

Best Practice#

Only release a phase for shipping when production, QC, and yard readiness have been reviewed.
If the phase was released too early or needs another operational check, use Unrelease for Shipping before continuing with dispatch preparation.
This keeps the shipping workflow controlled, traceable, and aligned with the actual readiness of the phase.

Entry to Shipping Yard#

This tab displays all items that were completed in production, passed QC, and are now waiting to be moved into the shipping yard.
Each card shows:
Phase
Item Mark
Quantity
Increment/Decrement buttons
Accept button
You can:
Accept items one by one
Accept multiple items by adjusting the quantity
Use Accept All to approve all pending entries in one click
Once accepted:
Items move into the official Shipping Status table
Their yard weight and status update accordingly

📦 Shipping Status (Main Table)#

This tab provides a complete view of all items already in the shipping yard or ready for shipping.

The table includes:#

Phase
Mark
Category
Profile
Unit Length
Total Quantity
Total Weight (t)
In Yard Weight
To Enter Weight
87ce45d4-fa9a-4f57-be39-7940f454f1e2.png
These values help shipping teams:
Validate quantities before loading
Prepare shipment batches
Reconcile physical vs. digital yard inventory

Tools Available#

Excel Export — For logistics planning or external reporting
PDF Export — For official documentation
Clear Filter — Reset all applied filters

How Shipping Status Works in the Workflow#

1.
Production finishes an item
2.
QC approves it
3.
Item appears in Entry to Shipping Yard
4.
Yard team accepts quantities
5.
Item’s weight and presence updates in Shipping Status
6.
Item becomes available for final shipment
This ensures traceability and prevents unauthorized or unrecorded yard entries.

⭐ Best Practices for Shipping Teams#

Always verify that QC approval is completed before accepting yard entries
Use Accept All only when daily QC and production batches are validated
Compare In Yard Weight with physical inventory weekly
Maintain accurate quantity adjustments when accepting items
Export reports monthly to ensure data backup and management review
Keep the Shipping Calendar updated to avoid conflicts in dispatch dates

🔗 Related Pages#

Tracking – Track production progress and stage completion
Quality Control – Approve items before yard entry
Shipping Calendar – View dispatch schedules
Production – Monitor items being manufactured
Reports → Shipping Reports – Analyze shipment performance