Review Project, Building, Phase, and Task timelines
Understand when tasks start and finish
Review the hierarchy between Projects, Buildings, Phases, and Tasks
Identify tasks that have not started on time
Monitor active and completed work
Expand the schedule for detailed operational review
Collapse the schedule for management-level visibility
Zoom in or out across the timeline
Review task information through tooltips
Export schedule information to Excel or PDF
The Projects available to the user
The Buildings and Phases inside those Projects
The tasks linked to each Project structure level
The Start Dates and Due Dates configured for the tasks
The current status of each task
A Project contains one or more Buildings
A Building contains one or more Phases
A Phase contains production, Quality Control, documentation, and shipping tasks
Which Project is currently active
Which Building has the longest schedule
Which Phase should already be in progress
Which tasks are running at the same time
Which tasks have not started as planned
Which tasks have been completed
Where Project execution may be at risk
When the Project schedule begins
When the Project schedule ends
The overall duration covered by its Buildings, Phases, and tasks
The general position of the Project within the displayed timeline
Which Building starts first?
Which Building finishes last?
Which Building has the longest schedule?
Which Building contains delayed tasks?
Are multiple Buildings being executed at the same time?
When the task should begin
When the task should finish
How long the task is expected to take
Whether the task is active
Whether the task has been delayed
Whether the task is completed
A short bar may represent a one-day review activity
A longer bar may represent a multi-week engineering activity
Overlapping bars indicate tasks scheduled during the same period
A bar positioned in the past may indicate delayed or completed work, depending on its status
The task is moving as planned
The Due Date remains achievable
The Assignee has the required inputs
Comments and attachments are updated
Work Logs are recorded where required
Blocking issues are documented
The Assignee has not started the task
A predecessor task is delayed
Required information is missing
The Start Date is no longer realistic
The task status has not been updated
The task has been overlooked
4.
Confirm whether the required inputs are available
5.
Update the task status if work has started
6.
Adjust the dates only when the schedule has genuinely changed
7.
Record the reason for the delay where appropriate
1.
Confirm whether the task is genuinely incomplete
2.
Review the current progress
3.
Confirm the responsible Assignee
6.
Update the Due Date only when the revised plan has been approved
7.
Add comments explaining the reason and next action
8.
Escalate tasks that affect critical Project commitments
Which activities were finished
Whether the planned sequence was followed
Whether related tasks can begin
Whether the Phase or Project summary is progressing
Historical execution timing
The Project schedule covers a long period
Tasks extend beyond the current visible dates
Users want to review the complete schedule span
A schedule is being presented during a meeting
The user has zoomed too far in or out
The task title clearly describes the work
The Start Date is correct
The Due Date is realistic
The status reflects actual progress
The Priority is appropriate
The task belongs to the correct Project, Building, or Phase
The task is not blocked by another activity
The schedule bar reflects the intended duration
Review the complete Project timeline
Compare Building and Phase schedules
Identify delayed activities
Review upcoming deadlines
Prepare progress meetings
Understand whether Project commitments are at risk
Review planned work across time
Identify work that should have started
Review overlapping activities
Coordinate upcoming tasks
Evaluate schedule duration
Support weekly planning meetings
Review production-related tasks
Identify upcoming Phase activities
Track work that is waiting to start
Follow up delayed production tasks
Understand the timing relationship between production and shipping
Review inspection-related tasks
Identify Quality Control activities approaching their Start Dates
Follow up overdue inspections
Understand whether Quality Control delays may affect shipping
Coordinate with production teams
Review packing and readiness tasks
Follow up shipping preparation
Identify activities delayed by production or Quality Control
Review planned dispatch-related deadlines
Coordinate with Project and Production teams
1.
Review the Project Summary bars
2.
Compare Building Summary bars
3.
Review Phase Summary bars
4.
Identify tasks marked Overdue
5.
Identify tasks marked To Do and Start Date Passed
6.
Review active In Progress tasks
8.
Review Assignees and Priorities through tooltips
9.
Expand delayed areas for more detail
10.
Record required follow-up actions
Upload Approved Drawings is Done
Review Phase BOM is Overdue
Release Phase for Production is To Do and Start Date Passed
Final Inspection is scheduled for the future
Prepare Packing List is scheduled after Final Inspection
1.
Open Task Manager → Schedule
3.
Review Project and Building summary bars
4.
Expand Projects requiring attention
6.
Identify To Do tasks with passed Start Dates
7.
Review In Progress tasks due during the week
10.
Export the schedule when required
1.
Create a template named Project Engineering Workflow
3.
Select the Template Start Date
4.
Fabritec creates the tasks
5.
Generated tasks receive Start Dates and Due Dates
6.
The tasks appear in Task Schedule View
7.
The team monitors progress across the timeline
Schedule View depends on accurate task Start Dates and Due Dates.
Tasks without realistic dates may reduce schedule accuracy.
Users should update task statuses when work begins or finishes.
A task may appear delayed if its status has not been updated.
Overdue tasks should be reviewed before their dates are changed.
Changing dates should reflect an approved schedule revision, not hide a delay.
Summary bars depend on the timing of the work displayed under them.
Expanding all rows may create a large schedule that requires more scrolling.
Use collapsed rows for high-level review.
Use expanded rows for operational analysis.
Exported Excel and PDF files are static snapshots.
The visible schedule depends on the user’s permissions and available Project data.
The task is linked to the correct Project, Building, or Phase
The task has valid scheduling information
The user has permission to view the linked entity
The relevant Project hierarchy is expanded
The schedule is positioned on the correct date range
Work has actually started
The status should be changed to In Progress
A predecessor activity is delayed
The Assignee has the required information
The Start Date needs an approved revision
Keep task Start Dates and Due Dates accurate
Update statuses when work begins
Mark tasks Done only after completion
Review overdue tasks regularly
Review tasks marked To Do and Start Date Passed before they become overdue
Start schedule reviews with Project Summary bars
Compare Building and Phase Summary bars before opening individual tasks
Use Expand All Tasks for detailed planning sessions
Use Collapse All Tasks for management reviews
Expand only the affected hierarchy when investigating a delay
Use tooltips for quick task checks
Use Zoom In for short-term schedule analysis
Use Zoom Out for long-term planning
Use Zoom to Fit when reviewing the full schedule
Review Schedule View during weekly planning meetings
Confirm Assignees and Priorities for delayed tasks
Review dependencies when one delay affects another task
Export to Excel for additional analysis
Export to PDF for fixed schedule reporting
Do not change dates only to remove overdue indicators
Record the reason when an approved schedule change is made