The Erection feature in Fabritec allows teams to track and update the site installation progress of project items after they have been shipped and delivered to the work site.It extends Fabritecβs execution visibility beyond production and shipping, helping teams monitor what has been produced, shipped, delivered, and finally erected on site.Activate erection tracking for specific projects
Track items across production, shipping, delivery, and erection stages
Confirm delivery receipt at the work site
Update erected quantities per item
Perform bulk erection updates for multiple items
View item details before updating erection progress
Monitor delivered, erected, and remaining quantities
Export erection progress to Excel or PDF
The Erection feature ensures that site installation progress remains connected to the same project, phase, item, and shipping data already managed inside Fabritec.
π Where to Find Erection
Projects β Select Project β ErectionThe Erection page appears inside the project menu, along with:
Activating Erection for a Project#
Erection is activated at the project level.When creating a new project, the user can enable erection tracking by selecting the Include erection checkbox in the New Project form.Important Note#
Once Include erection is activated and the project is created, it cannot be deactivated later.This option should only be selected for projects that require site erection or installation tracking.
How to Activate Erection#
3.
Fill in the project information: After the project is created, the Erection page becomes available inside the project.
Erection Workflow#
The Erection workflow starts after the normal production and shipping process.Production β Shipping Yard β In Transit β Delivered but not erected β ErectedEach status represents the current operational position of the item.| Status | Description |
|---|
| Production | The item is still under production or has not yet reached the shipping flow. |
| Shipping Yard | The item is completed and available in the shipping yard. |
| In Transit | The item has been shipped but has not yet been confirmed as delivered to the work site. |
| Delivered but not erected | The item has arrived at the work site but has not been erected yet. |
| Erected | The item has been installed or erected on site. |
Confirming Delivery to Site#
Before an item can be updated as erected, the related shipment must first be confirmed as delivered to the work site.This is done from the Shipping page.Confirm Delivery Steps#
To confirm that a shipment has arrived at the work site:3.
Locate the required dispatch.
4.
In the Actions column, click the Confirm Delivery icon.
5.
The Confirm Delivery popup will open.
After delivery is confirmed, the related items move into the erection workflow as Delivered but not erected.
Erection Page#
The Erection page is the main workspace for tracking and updating site erection quantities.Projects β Select Project β ErectionAt the top of the page, you can select:This allows users to focus on a specific project and one or more selected phases.
Main Actions#
The Erection page includes the following actions:These tools help users manage large erection datasets, export progress, and control the table view.
Erection Status Tabs#
The Erection page includes status tabs that help users filter items based on their current lifecycle stage.Delivered but not erected
All#
Displays all items included in the erection lifecycle, regardless of their current status.Use this view when you need a complete overview of all project items related to erection tracking.
Production#
Displays items that are still in production.These items are not yet delivered to site and cannot be marked as erected.
Shipping Yard#
Displays items that have completed production and are available in the shipping yard.These items are ready for shipment but have not yet reached the site.
In Transit#
Displays items that have been shipped but not yet confirmed as delivered to the work site.Once delivery is confirmed, the items move to Delivered but not erected.
Delivered but not erected#
Displays items that have arrived at the work site but still need to be erected.This is the main working tab for site teams when updating erection progress.Erected#
Displays items that have been fully erected on site.When the erected quantity equals the delivered quantity, the item progress becomes 100% and the status changes to Erected.
Erection Table Columns#
The Erection page displays item-level erection data in a structured table.| Column | Description |
|---|
| Building | The building or model related to the item. |
| Phase | The phase linked to the item. |
| Mark | The item or assembly mark. |
| Operation Type | Indicates whether the item is Manufacture, Outsourcing, or Stock. |
| Category | The item category, such as Hot Rolled or Trusses. |
| Status | The current lifecycle status of the item. |
| Qty | The total item quantity. |
| Erection Quantities | Shows Delivered, Erected, and Remaining quantities. |
| Profile | The item profile or specification. |
| Drawing | The linked drawing file, if available. |
| Total Weight | The total item weight. |
| Progress | The erection completion percentage. |
| Actions | Allows users to update erection quantity or view item details. |
Erection Quantities#
The Erection Quantities column shows three important values:Delivered: Quantity received at the work site
Erected: Quantity already erected on site
Remaining: Quantity still pending erection
Delivered: 111
Erected: 0
Remaining: 111
Delivered: 111
Erected: 111
Remaining: 0
When the remaining quantity becomes zero, the item progress becomes 100%.
Updating an Item as Erected#
You can update the erection progress of a single item from the Actions column.This is used when a specific item has been erected on site and the quantity needs to be recorded in Fabritec.Steps to Update a Single Item#
1.
Navigate to Projects β Select Project β Erection.
2.
Open the Delivered but not erected tab.
3.
Locate the item you want to update.
4.
Click the purple Update button in the Actions column.
5.
The Update popup will open.
6.
Review the item information: After saving, Fabritec updates the erected quantity and recalculates the remaining quantity and progress percentage.
| Field | Description |
|---|
| Mark | The item mark being updated. This field is filled automatically by the system. |
| Phase | The related project phase. This field is filled automatically by the system. |
| Operation DateTime | The actual date and time of the erection update. |
| Qty | The quantity erected on site. |
| Units | The quantity unit used for the update. |
Important Update Rules#
Only update quantities that were actually erected on site.
Do not enter a quantity greater than the delivered remaining quantity.
Use the correct operation date and time for accurate tracking.
If multiple items were erected together, use Bulk Update instead of updating each item one by one.
Bulk Update#
The Bulk Update feature allows users to update multiple erected items at once.This is useful when several marks are erected during the same site activity or on the same date.
When to Use Bulk Update#
Multiple items were erected at the same time
A site team completed several marks during one operation
You need to save time instead of updating items individually
You want to apply the same operation date and time to multiple records
Steps to Use Bulk Update#
1.
Navigate to Projects β Select Project β Erection.
2.
Select the required items using the checkboxes.
4.
Set the Operation DateTime at the top of the screen.
6.
Adjust quantities if needed.
7.
Click Save for individual rows, or click Update All to update all selected items.
8.
Click Close when finished.
Bulk Update Fields#
| Field | Description |
|---|
| Operation DateTime (apply to all) | Applies the same operation date and time to all selected items. |
| Mark | The item mark selected for update. |
| Phase | The phase linked to the item. |
| Operation DateTime | The operation date and time for each item. |
| Qty | The quantity to be marked as erected. |
| Actions | Allows the user to save or remove an item from the update list. |
Bulk Update Result#
After clicking Update All:Erected quantities are updated
Remaining quantities are recalculated
Progress percentages are updated
Fully completed items move to the Erected tab
Partially completed items remain visible until fully erected
Exporting Erection Data#
The Erection page supports exporting data for reporting and follow-up.Available export options:Installation progress documentation
Search, Filters, and Columns#
The Erection page includes operational controls to help users manage large projects.Search#
Use the search bar to find items by mark, phase, category, or other visible data.Clear Filter#
Removes applied filters and returns the table to the default view.Columns#
Allows users to show or hide table columns based on what they need to review.Reset Cache#
Refreshes the table data when needed.
Erection Progress Logic#
Erection progress is calculated based on delivered quantity and erected quantity.Total Qty: 111
Delivered: 111
Erected: 0
Remaining: 111
Progress: 0%
After updating the erected quantity:Total Qty: 111
Delivered: 111
Erected: 111
Remaining: 0
Progress: 100%
When the full delivered quantity is erected, the item status becomes Erected.
Operational Workflow Summary#
The Erection feature follows this lifecycle:1.
Create a project and activate Include erection.
2.
Complete the production workflow.
3.
Move items through the Shipping Yard.
4.
Create and confirm shipment.
5.
Confirm delivery receipt at the work site.
7.
Review items under Delivered but not erected.
8.
Update erected quantities.
9.
Track remaining quantities and progress.
10.
Confirm completion when items reach Erected.
Common Use Cases#
Site Installation Tracking#
Track which delivered items have been installed and which are still pending.Project Progress Control#
Monitor site execution progress after production and shipping are completed.Delivery-to-Erection Follow-up#
Compare delivered quantities against erected quantities to identify pending work.Client Reporting#
Provide structured progress updates using exported erection data.Quantity Dispute Review#
Open Item Details to verify production, shipping, and item history before making updates.
Common Mistakes to Avoid#
Creating a project without activating Include erection when site installation tracking is required.
Trying to deactivate erection after the project is created.
Updating erected quantities before confirming delivery to the work site.
Entering full quantity as erected before site confirmation.
Confusing Delivered with Erected.
Updating the wrong phase when multiple phases are selected.
Using single update for many items instead of Bulk Update.
Best Practices#
Activate Include erection only for projects that require site installation tracking.
Confirm delivery immediately when items arrive at the work site.
Use Delivered but not erected as the main working view for site updates.
Use Bulk Update for multiple items erected during the same site activity.
Review Item Details before updating items with unclear quantities.
Keep project and phase filters accurate to avoid updating the wrong records.
Export erection data regularly for project progress meetings.
Ensure site teams update quantities based on actual erected work, not planned work.
Governance Model Summary#
The Erection feature is built around three operational controls:1.
Project Activation Control
Erection must be enabled when creating the project.
2.
Delivery Confirmation Control
Items must be confirmed as delivered to site before erection updates are recorded.
3.
Quantity Progress Control
Delivered, erected, and remaining quantities are tracked at item level.
Clear site progress visibility
Controlled quantity updates
Accurate installation tracking
Better coordination between factory, logistics, and site teams
Full traceability from production to erection completion
π Related Articles#
Modified atΒ 2026-06-02 09:29:53